PUBLIC NOTICE
ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT
NOTICE OF PROPOSED AIR PERMIT FOR PREVENTION OF SIGNIFICANT DETERIORATION (PSD)
AND REQUEST FOR COMMENTS
FACILITY NO. 106-0010
MONROE COUNTY
On December 27, 2024, Alabama River Cellulose, LLC submitted a Prevention of Significant Deterioration (PSD) Permit application for a proposed project to increase efficiency and reliability of the No. 7 Mill and to optimize production. The application was deemed complete on July 25, 2025. This facility is located at 2373 Lena Landegger Highway in Perdue Hill, Alabama.
The proposed modification is subject to the requirements of the Prevention of Significant Deterioration (PSD) regulations as set forth in ADEM Admin. Code r. 335-3-14-.04. An ADEM-Air Division technical staff preliminary determination indicates:
Pollutant | % NAAQS Consumption |
---|---|
PM10, 24-hour | 4.45 |
PM10, Annual | 2.14 |
PM2.5, 24-hour | 18.97 |
PM2.5, Annual | 7.58 |
NO2, 1-hour | 13.70 |
NO2, Annual | 0.67 |
CO, 1-hour | 0.66 |
CO, 8-hour | 1.42 |
ADEM has determined that the limitations proposed by the company would properly limit emissions.
The following are links to the preliminary determination and permit application:
Preliminary DeterminationPersons wishing to comment may do so, in writing, to the Department’s named contact below within 30 days following the publication date of this notice. In order to affect final decisions, comments must offer technically substantial information that is applicable to the proposed application. All comments must be received no later than 5:00 p.m., September 3, 2025.
Aubrey H. White III, Chief
ADEM-Air Division
1400 Coliseum Blvd.
[Mailing address: PO Box 301463; Zip 36130-1463]
Montgomery, AL 36110-2400
(334) 271-7861
A written request for a public hearing may also be filed within that 30-day period and must state the nature of the issues proposed to be raised in the hearing. The Director shall hold a public hearing whenever it is found, on the basis of hearing requests, that there exists a significant degree of public interest in the permit application.
After consideration of all written comments, review of any public hearing record, and consideration of the requirements of the Alabama Air Pollution Control Act, the Federal Clean Air Act and applicable regulations, the Department will make a final determination. The Department will develop a response to comments, which will become part of the public record and will be posted to the Department’s eFile system.
Copies of the complete project file are available for public inspection Monday through Friday (except legal holidays), 8:00 a.m. to 5:00 p.m., at the ADEM Main Office at the address listed above. For convenience, documents that exist in electronic format may be accessed in the Department's document management system, eFile. To view these documents, select Media Area “Air”, enter the facility number shown above as the Permit Number, select Document Type “Permitting”, and press Search. The most recent documents will be listed at the top by default. The Document Type may also be left blank, which will list all electronically available air files for this facility.
The Department maintains a list of interested individuals who are mailed legal notices regarding proposed permits. If you wish to receive such notices, please sign up here.
This notice is hereby given this 4th day of August, 2025, by authorization of the Alabama Department of Environmental Management.